[CCCure CISSP] Question on BIA
An.Dang at do.treas.gov
An.Dang at do.treas.gov
Mon Mar 22 12:11:54 EDT 2010
I think "priorities" is more important in a contingency plan for disaster recovery. "Dependencies" and "service levels", I think, are better answers for this question.
-----Original Message-----
From: cisspstudy-bounces at cccure.org [mailto:cisspstudy-bounces at cccure.org] On Behalf Of cisspstudy-request at cccure.org
Sent: Monday, March 22, 2010 12:00 PM
To: cisspstudy at cccure.org
Subject: CISSPstudy Digest, Vol 21, Issue 27
Send CISSPstudy mailing list submissions to
cisspstudy at cccure.org
To subscribe or unsubscribe via the World Wide Web, visit
http://cccure.org/mailman/listinfo/cisspstudy_cccure.org
or, via email, send a message with subject or body 'help' to
cisspstudy-request at cccure.org
You can reach the person managing the list at
cisspstudy-owner at cccure.org
When replying, please edit your Subject line so it is more specific
than "Re: Contents of CISSPstudy digest..."
Today's Topics:
1. Question on BIA (Anees Ghosh)
----------------------------------------------------------------------
Message: 1
Date: Mon, 22 Mar 2010 01:07:06 -0500
From: Anees Ghosh <aneesghosh at hotmail.com>
To: <cisspstudy at cccure.org>
Subject: [CCCure CISSP] Question on BIA
Message-ID: <SNT136-w104380A00592357A61719CC8270 at phx.gbl>
Content-Type: text/plain; charset="iso-8859-1"
Hi,
I found the following quesiton on freepracticetests.org and am confused about the answer.
Which of the following should be emphasized during the business impact analysis (BIA) considering that the BIA focus is on business processes?
composition
priorities
dependencies
service levels
The correct answer is "dependencies" with the following explanation.
In performing the Business Impact Analysis (BIA) it is very important to consider what the dependencies are. You cannot bring a system if it depends on another system to be operational. You need to look at not only internal dependencies but external as well. You might not be able to get the raw materials for your business so dependencies are very important aspect of a BIA.
My thoughts are as following: The BIA phase helps the organization identify the business processes and MTD for each. Based on the MTD, and financial impact a priority is defined and then further analysis is done to ensure this process is part of the BCP plan. Shouldnt priority be the answer? After the critical process is identified, this is when we will ensure all dependiencies are taken care of.
Appreciate the help!
Regards
Anees Ghosh
_________________________________________________________________
Hotmail has tools for the New Busy. Search, chat and e-mail from your inbox.
http://www.windowslive.com/campaign/thenewbusy?ocid=PID27925::T:WLMTAGL:ON:WL:en-US:WM_HMP:032010_1
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://cccure.org/pipermail/cisspstudy_cccure.org/attachments/20100322/5b9434fc/attachment-0001.html>
------------------------------
_______________________________________________
CISSPstudy mailing list
CISSPstudy at cccure.org
http://cccure.org/mailman/listinfo/cisspstudy_cccure.org
End of CISSPstudy Digest, Vol 21, Issue 27
******************************************
More information about the CISSPstudy
mailing list